AWHC route protection moving ahead

I was recently sent a briefing from late May that the NZTA gave to the transport industry on the three large projects in Auckland that will be procuring work for. In all cases the work relates to designation and planning work and the projects are the Additional Waitemata Harbour Crossing (AWHC), the Northern Corridor works and the East-West link. The most interesting of them and the one I’ll cover here is the AWHC.

The NZTA intend on restarting the process to get protect the route that they put on hold in 2009. This was actually announced back in in 2013 the government launched their programme of ‘accelerating’ a number of motorway projects. Interestingly they say here it will cost around $4 billion. This is just another in the long list of wild estimates for this project and of course won’t include any works necessary to widen the Northern Motorway to be able to handle the extra traffic or increase the capacity of the CMJ – which I’m told is all built out.

AWHC - Indstry Briefing

That cost also won’t include any costs to connect the rail tunnels at each end shown in the image (closer look below) meaning that it’s likely any idea of rail to the shore will be dependent on a separate project and one that will likely fail any business case for some time thanks to the presence of the recently built motorway.

AWHC Tunnel cross section

Perhaps the most interesting part is this slide showing that building the tunnels induces a lot more demand. It would be interesting to know if they are talking about all trips or just vehicle trips. If the latter the increase is probably because it would undermine the busway therefore seeing people moving back to driving.

AWHC - Induced Demand

It’s also still not clear that vehicle demand is going to increase by that level. For a start no one knows just what impact the completion of the Waterview and the Western Ring Route will have and even without that traffic volumes haven’t been increasing like they were predicted to. I most recently looked at volumes here.

AHB Annual Volumes to 2014

This slide shows the next steps in the process

AWHC - Route Protection process

And here’s the scope of the current works planned

AWHC -Route Protection scope

Interestingly this just went public yesterday

The NZ Transport Agency invites Registrations of Interest (ROI) from suitably experienced consultants and advisors who have the right people with the necessary vision, experience, capacity, understanding and commitment to deliver outstanding outcomes for the Additional Waitematā Harbour Crossing (AWHC).

The professional services for route protection will be procured using the staged delivery model. The contract will be finalised through a negotiation phase, which will develop an agreed methodology, effort, target fee and pain/gain approach.

Scope

The high level objective of the project is to complete the route protection and secure designations for the AWHC; by updating and confirming the existing Notices of Requirement (NoRs), and serving new NoR(s), as required to designate the land at either end of the additional crossing. This project is to be publicly notified and a public hearing is likely to occur.
Skills Required

The team will generally provide the following expertise, but not be limited to:

  • Statutory planning and resource management
  • Engineering, including tunnelling, highway, rail, civil engineering and geology/geotechnical
  • Traffic modelling and transport planning
  • Environmental and social management, technical expertise and assessment
  • Provision of evidence at hearings and expert witness

Request for Proposals Overview

The Request for Proposal (RFP) will use the quality based supplier selection method. The contract scope will be reasonably broad and focused on key outcomes with the approach and related scope to be further defined by respondents.

A RFP interactive presentation, for all respondents, is proposed to be held after the RFP closes, and will be assessed as part of the evaluation.
RFP documents will only be issued to those applicants who have submitted an ROI.

Industry Briefing

Prospective respondents to this ROI are invited to attend an Industry Briefing on Thursday 2 July 2015. Respondents wishing to attend this briefing are requested to confirm their interest in attending before 4:00pm on Tuesday 30 June 2015. Attendees will be limited to two per company.

ROI Response

The ROI will be open for three weeks and will close at 4:00pm on Thursday 9 July 2015.

In my view, before we build any more road crossings our transport agencies should be prioritising their focus on getting the missing modes across the harbour. That means Skypath needs to be built as soon as possible (we should hear the results of the resource consent within 2 weeks) and then the focus needs to be on a dedicated PT route. That would provide much greater additional capacity and resilience for less cost than a the huge road tunnels planned and could happen sooner. In face it could even possible link in with the light rail plans for the isthmus – more on that in another post. Route protection wouldn’t stop that outcome but our agencies need to have a serious rethink of the project in its current form.

The Devonport-Parnell Bridge

Digging around online the other day I came across an Auckland Council Archives webpage with a series of old plans and charts on early Auckland harbour bridge and tunnel concepts. I do recommend having a poke around for fans of this sort of thing.

The one plan that really caught my eye was the one below, a 1930s concept for a suspension bridge from Devonport to Parnell.  Click this link for the full size version. 

ACC 015 - 7853-004, proposed bridge layout 1930s

Look at that: tall towers with graceful parabolas of cable holding up a long spanning slender deck. Boy I do love a good suspension bridge! And check the engineers stamp in the bottom right corner. None other than J.J. Bradfield himself, designer of both the Sydney Harbour Bridge and the connected City Circle underground rail system.

With 175 feet (54m) clearance above the water this would have had more room under it than our existing bridge, however it would have ended up on the wrong side of the modern container port. If they had built this perhaps the port would have been forced to move out by now.

The four lanes and two tram tracks sounds like just what we need today, if you could squeeze in a footpath and cycleway. Having said that, you can presume the trams would have been ripped out and the bridge converted to a six lanes all for traffic like so many bridges from that era.

I also wonder what would have become of the motorway system without the harbour bridge to Northcote Point, presumably spaghetti junction would have ended up further east and Parnell would be sliced in half by a motorway. Would we lament the swathe carved through Devonport and Bayswater the way we lament the long gone villas of Newton gully and the lost beaches at St Marys Bay, or would we simply forget like we have the City of Cork Beach? Perhaps the Eastern Motorway would have been built, perhaps instead of the Southern?

In any case, the shape of our city would have been considerably different. A reminder that new transport infrastructure shapes our future city as much as it responds to our existing one.

…and doesn’t it make our actual bridge look like an ugly bugger in comparison?

How business groups view transport

Yesterday the Auckland Business Forum sponsored four pages of op-eds in the business section of the Herald about the need to improve transport for businesses. Unfortunately it ended up being a bit of a case of who left the gates to Jurassic Park open and let the Roadasaurs out.

Business Forum Jun 15

You can see all four pages below.

Page 1

Page 2

Page 3

Page 4

Perhaps the most hilarious of the pieces comes from the head of the National Road Carriers – a trucking lobby group – who effectively suggests that a Mad Max style apocalypse is imminent unless we take quick action to speed up the movement of trucks.

When trucks gridlock, Auckland stops. Virtually everything manufactured, imported, bought or consumed in Auckland is at some point transported by truck.

If truck movement stopped in Auckland, within the first 24 hours service stations would begin to run out of petrol, supermarkets and restaurants would have no fresh food, building sites and assembly companies using just-in-time suppliers would experience materials and parts shortages, and mail and other package deliveries would cease.

After a couple of days, food shortages would develop, motor vehicle fuel availability would dwindle, exports and imports of goods by sea and air would cease, as would operations of many wholesale and retail businesses. Thousands of Aucklanders would soon be out of work.

This demonstrates the critical importance of freight and goods delivery within Auckland’s transport system — when trucks can’t move, Auckland stops.

Freight is the backbone of the Auckland economy. It figures that if we are serious about improving our economy, we must get serious about tackling Auckland’s worsening traffic congestion and improving our productivity and efficiency.

As Auckland’s population grows, it is critical that we stop congestion spreading through the whole of the working day as it is starting to do in some areas of the city.

His other article suggests some of the ways trucks can be avoided where he suggests that trucks should be able to use the busway and bus lanes.

His big priority is the east-west link which he wants the government to take over and build as a RoNS – because you know it’s not like the NZTA is sitting around doing nothing. He suggests that a route along the waterfront on the Northern edge of the Mangere Inlet is good because it will “avoid community severance” and encourage the repair of the “environmentally damaged reclaimed land”. I know some Onehunga Foreshore groups support this option because they think they will get a new foreshore – like what is being done now next to the motorway – on the northern side of the inlet. Of course not that anyone will be able to easily access it due to the severance the motorway they want causes.

Seeing as this route is claimed to be so vitally important for truckies, I wonder how much they’re prepared to pay to use it – or are they expecting this to be a massive subsidy from the public towards their operations.

Herald East-West link graphic

Also pushing to keep the trucks moving is a representative of the construction firms. In this case he’s primarily talking about trucks involved in construction. A case of the trucks must get through to be able to build more roads that will also end up congested. It’s a bit like groundhog day. He also calls for trucks to be able to use busways. He is of course correct when he says:

At the heart of an Auckland-Wellington strategy must be an accelerated effort to improve the city’s public transport system. Getting single-occupancy commuter vehicles off Auckland roads during the day would free up the capacity for contractors, transport operators and other essential trades.

However a few paragraphs later he then undoes that by stating that PT should only be funded if it doesn’t get in the way of building new stuff.

Meanwhile, increased public transport funding is only viable if it does not impact on the activities of the people who build the city.

One area I do agree with him on is in his other piece where he suggests there might be some advantages to merging the local aspects of the NZTA and Auckland Transport. I’d go further and suggest the rail network should also be included. A single agency managing the entire transport network could be useful if it also coincided with more autonomy in how the money is spent rather than the rigid Government Policy Status. That could mean motorway, PT and local road and even rail freight projects could be treated equally but there is little chance the government would allow this.

Stephen Selwood from the NZCID has also written a few pieces. In one notes that the current plans for an Additional Waitemata Harbour Crossing add no new connectivity and that it wastes the transport budget. His solution to this is to make the tunnel longer and instead connect up to the eastern side of the CBD. However not content with that he also wants to revive the Eastern Motorway and suggests it be built as a tunnel so it “protects the views and amenity of the eastern suburbs”. It would then presumably link up with a larger AMETI project.

If the AWHC is estimated at $5 billion then how much is an approximately 14km tunnel from Glen Innes to the North Shore going to be?

Lastly both Selwood and Chamber of Commerce CEO Michael Barnett separately talk about and support the governments push for a transport accord. While I don’t necessarily disagree it seems that are taking the stance that Auckland’s current plans are fundamentally wrong. In my view we’ve seen a huge improvement in the work AT has done in it’s planning for the future and it’s starting to show that the plans of the past aren’t necessarily right or worth pursuing. This has been shown in examples like how they’re thinking of deferring the Reeves Rd flyover which would have just shifted congestion one intersection down the road and to invest the money in bringing forward PT improvements. Another is them looking at light rail as way of addressing looming bus congestion.

Of course there’s also the irony that the business groups are supporting the government in creating another year of delay and debate while also calling for urgent action to speed things up. Perhaps it’s time to stop having a bet each way and pick a position. To me it also shows why it’s so vital that we don’t just leave the conversation about Auckland’s future to these influential and well connected groups.

An Alternative AWHC

Two weeks ago the government once again talked about an Additional Waitemata Harbour Crossing (AWHC). There are a number of reasons why another road based crossing is not a great idea – and even the Herald has been sceptical about it – but perhaps the biggest issue of all is the sheer cost of it. It’s been estimated to cost a whopping $4 billion to $6 billion. That’s considerably larger than what we spend on transport for the entire nation each year and about 5 years’ worth of the entire transport budget for Auckland. However the announcement once again got me thinking about what else we could do if we had $4-$6 billion to spend.

Anyone who has read this blog for long enough will know that our preference is for the money to go towards advancing projects on the Congestion Free Network.

Of course even by the time-frame the government suggest of 2025-30 we’d hope that much of the CFN would have been completed or at least already well under way. So I thought, what could we do if we were to spend that $4-$6 billion to further enhance the CFN. As a basis I was reminded of this old post by Nick R looking at something similar to Vancouver’s Skytrain – something sometimes referred to as Light Metro.

One of the useful aspects is that from Vancouver we have a couple of good recent examples of how much such a system may cost.

  • The Canada line was built in 2009 for a cost of just over $2 billion Canadian dollars (about NZ $2.5 billion once you account for exchange rates and inflation etc.). For that price they got 16 stations (8 underground, 6 elevated) on 19.2km of double track (including 9.1km in tunnels, 7.3km elevated and a 614m long bridge). It also includes 20 two-car driverless trains to run on it plus a maintenance facility. All up it cost them about $130 million per km.
  • The Evergreen Line is an extension currently under construction for a cost of $1.4 billion Canadian dollars (NZ$1.5 billion). It will be 10.9km of double track of which 2km is underground and much of the rest is elevated. It also includes six new and one redeveloped station and the existing Skytrain fleet will be boosted by 28 new Skytrain cars (14 two-car trains?). All up the cost is about $137 million per km.

Using a figure of $140 million per km it might deliver us somewhere between 28 and 43km of light metro network which is quite a lot. So what could we get with that?

One potential option is a two line light metro network linking up parts of the North Shore and also the Northwest. Something like below which features both a North Shore and Northwest line. Both pass through the City Centre and under the harbour in a shared tunnel then have short spur off to the Metropolitan Centres of Newmarket and Takapuna. Both lines could be extended further in the future towards Silverdale in the North and Kumeu in the Northwest. In the City Centre it would provide good rapid transit access to areas not covered directly by the CRL.

Light Metro North & Northwest

With automatic trains the shared sections could see trains every two minutes. That’s 30 trains an hour or up to 15 trains an hour on each line. Combine that trains carrying 500-600 people each and we’d have the capacity to easily move 15-20 thousand of people direction every hour free of traffic congestion. As a comparison a road crossing with three lanes each way might carry 6,000 people per hour in each direction.

By now some of you may be concerned about thinking too much along the line of using Light Metro in case it delays the already needed Northwest Busway. It’s definitely a legitimate concern however I feel there’s no reason the busway couldn’t be built sooner but designed to be easily upgradeable later on.

This also raises another key point in favour of a solution like this compared to the AWHC. With the AWHC the entire $4-$6 billion project has to be done in one big burst whereas with a network like this it could easily be broken up into smaller stages. For example we could do something like this:

  • Stage 1 – Takapuna to Aotea with bus/train interchanges at Akoranga and Onewa Rd.
  • Stage 2 – Akoranga to Albany replacing the busway.
  • Stage 3 – Aotea to Newmarket
  • Stage 4 – Northwest

Tying it all in with the other parts of the Congestion Free Network plus Auckland Transport’s Light Rail plans for the central Isthmus might look something this.

CFN 2030 + Light Metro

Given the option of a road tunnel under the harbour or an automated, high frequency rapid light metro system covering the North Shore and the Northwest I know which option I’d choose.

How would you spend the $4-$6 billion expected cost of an Additional Waitemata Harbour Crossing

View Results

Loading ... Loading ...

Additional Harbour Crossing back on agenda

The government has announced it is restarting the process to protect the route for an a third harbour crossing that raises a huge number of questions.

New Waitemata Harbour crossing future proofed

Minister of Transport, Simon Bridges, has taken steps to future-proof the route for an additional Waitemata Harbour crossing in view of the rapid growth Auckland is set to undergo in the next 20 years.

“I have asked the NZ Transport Agency to recommence work on what will be a critical transport link for Auckland and the upper North Island.

“The preferred route for the additional crossing is a tunnel east of the Auckland Harbour Bridge between the Esmonde Road interchange on the North Shore, and Victoria Park Tunnel and Central Motorway Junction in central Auckland.

“Advisors are preparing for the designation process and are putting together a business case focusing on the timing of construction and potential funding options,” Mr Bridges says.

In 2013 the Government announced its support for a tunnel in preference to a bridge.

“With increasing demands on Auckland’s transport network, the Government will continue to work closely with its local government partners to provide a resilient network and wider transport choices,” Mr Bridges says.

The NZ Transport Agency says an additional crossing is likely to cost between $4 billion and $6 billion, and is likely to be needed between 2025 and 2030. A construction start date will depend on a number of factors, including the rate of freight and traffic growth.

Mr Bridges says that the additional Waitemata Harbour crossing will work in conjunction with the existing Auckland Harbour Bridge.

The business case will look at a range of public transport options, including heavy rail. The NZ Transport Agency and Auckland Transport will be working together on this part of the project, including any necessary route protection for public transport.

“The Government knows that investment in all modes of transport will ease congestion and bring lasting benefits for Auckland and for New Zealand as a whole,” Mr Bridges says.

The NZTA last studied an additional crossing five years ago and the reports from that study are available here. The questions I have are in no particular order.

With construction depending on factors such as traffic growth, will the new business case take into account the actual traffic volumes from the last 8+ years. After almost 50 years on constant increases, traffic volumes fell after 2006 and have been so stubbornly flat that they are still less than they were in 2003. Not only did the previous business case – produced in 2010 – predict growth that hasn’t materialised but they also used a model to predict the volume for the starting year of their prediction (2008) which was well above the observed actual volumes.

AHB Volumes

Related, what will be the employment and traffic volume targets the project must achieve. After all if the City Rail Link is going to have bogus targets foist upon it then why shouldn’t the single most expensive project we’ve ever considered.

With the project costing between $4 and $6 billion how will we pay for it. To put things in perspective we currently spend about $3.4 billion on transport per year for the entire nation and that includes costs for state highways, NZTA contributions towards local roads, road policing, and of course NZTA contributions towards public transport. Within that budget we spend $1 to $1.4 billion on state highway improvements. In short an AWHC would suck up massive amounts of cash and that would impact on a huge numbers of projects from all around the country. Even if built as a PPP the ongoing payments would likely cripple our transport budgets for decades. As an example Transmission Gully which is costing around $850 million will have repayments once it opens of about $125 million a year. AWHC would be significantly more than that.

Will the business case achieve a Benefit Cost Ratio of greater than the 0.3 it did last time (Answer: presumably it will because of the changes since then to the NZTA’s Economic Evaluation Model allowing for a longer assessment period and reduced discount rate – still won’t be above 1 though)

AWHC 2010 BCR

It’s all very well talking about a horrifically expensive tunnel under the harbour but what constantly seems to be ignored is what happens on either end of the tunnel. Studies prior to the 2010 one have talked about how any new crossing would also require major expansions to the Northern Motorway to cope with the increased capacity thrown at. How much is it going to cost to duplicate SH1 to Albany and beyond? If not then we just get this situation.

WestConnex

What impact will the $4 billion we’ve been spending to create the Western Ring Route have on traffic and travel behaviour. At the very least we should probably be waiting till after that work is completed and traffic volumes have settled down before we do any analysis of traffic demand over the harbour.

WRR project location

Regardless of how much it costs or what the benefits are one fact that can’t be ignored is that this project will have major impacts on the environment it passes through. It effectively creates a new motorway out in Shoal Bay with all the red hatched parts in the images below being reclamation and the blue parts being viaducts. I wonder what the likes of the Herald’s John Roughan will say about – note:  I still don’t think he’s admitted he was wrong about the Northern Busway.

AWHC north of Onewa AWHC Sulhur Beach

Further if some of the residents of Northcote got so upset about the idea of Skypath, I wonder what they’ll think of having a mini spaghetti junction on their doorstep. Even more so when they realise that the two square boxes on the image above where the new lanes change from tan to purple colour (to the right of the 1 symbol) are 35m high (~10 storey) ventilation stacks for the exhaust fumes inside the tunnel. There is also one on the city side next to the current Air NZ building (below).

AWHC Westhaven

One mini positive is that the government are at least saying the business case will consider a rail crossing however in my mind the NZTA also need to assess options that involve building a PT only crossing first. A dedicated PT crossing along with Skypath are the real missing modes across the harbour. This is especially important given the huge growth we’re seeing in bus passengers from the shore and in the morning we’re seeing up to 30-40% of people crossing on a bus – up from 18% in 2001. This growth in PT is likely to continue for some time yet, especially once the new network eventually makes PT much more useful to a wider variety of people. One risk is I suspect there are quite a few people behind the scenes that will think an acceptable solution to PT across the harbour is just to leave it on the existing bridge.

Car and Bus trips across AHB

The 2010 and 2011 car results seem like they could be incorrect but I can’t confirm it

 

Overall route protection itself isn’t a bad thing but any suggestion that this is project is needed any time soon is fanciful thinking. There are far greater priorities in Auckland such as the CRL and significant upgrades to PT in many other areas. The government should be focusing on getting those projects consented and underway first.

Is road funding a case of “survival of the un-fittest”?

In several recent posts I’ve taken a look at people’s revealed preferences for roads (nobody’s willing to pay directly for them) and public transport, walking, and cycling (people are queuing up to get on the train). In those posts, I’ve argued that observing how people vote with their feet (or their wallets) can teach us a lot about demand for different travel modes.

BRITOMART_4116

Rail is now growing too fast to be un-fit for survival.

But as any economist knows, markets have two sides to them: demand and supply. As transport infrastructure has a lot of “public good” characteristics, it tends to be provided by government agencies such as Auckland Transport and the New Zealand Transport Agency. (These agencies wouldn’t say no if a private company turned up and offered to build a new motorway at no cost to them… but that’s not going to happen any time soon due to the fact that most recent private toll roads have failed financially.)

As a result, we have to consider how transport agencies make decisions about what to supply to the market. I’ve written a few posts on the basics of cost-benefit analysis, which is one of the tools that they use to decide which projects to build.

But is cost-benefit analysis robust, or are the results systematically biased in a certain direction? Thinking about this question led me to re-read one of my favourite papers on infrastructure costings (don’t laugh!): Bent Flyvbjerg’s “Survival of the Un-fittest: Why the Worst Infrastructure Gets Built – and What We Can do About It” (fulltext pdf). Flyvbjerg takes an empirical look at hundreds of major infrastructure projects around the world, finding that cost overruns are all-pervasive:

  • 9 out of 10 projects have cost overrun.
  • Overrun is found across the 20 nations and 5 continents covered by the study.
  • Overrun is constant for the 70-year period covered by the study, cost estimates have not improved over time.

In addition, benefits are systematically overestimated in ex-ante evaluations. The result is that a number of bad projects get built on the back of over-optimistic business cases. Flyvbjerg attributes this to “cognitive and political biases such as optimism bias and strategic misrepresentation”. (This is a polite way of saying “lying about the project to ensure that it gets built.”)

So how do New Zealand’s transport agencies stack up against Flyvbjerg’s analysis? Fortunately, we’ve got some empirical data to investigate this question with. Between 2009 and 2012, NZTA conducted and published a number of post-implementation reviews of (mainly) road projects that it funded in part or fully. Matt did an excellent job summarising the data in a post last year.

While the projects aren’t necessarily representative of all road projects, they do run the gamut from small pavement upgrades to multimillion state highway expansions. NZTA provided data comparing ex-ante and ex-post evaluations of costs and benefits for 69 projects in total. I subjected the data to some basic statistical analysis, finding that:

  • The average project had a cost overrun of 34% – a difference that was found to be highly statistically significant, meaning that there is a less than 1% probability that the observed difference happened by chance.
  • The average project had actual benefits that were 28% lower than expected – although as this difference was not statistically significant we can’t determine whether it simply reflects random chance.

In other words, NZTA and regional transport agencies seem to have had some issues accurately costing road projects. And the errors they are making are not random – they have systematically underestimated costs. This can be seen really clearly if we graph the data in histogram format.

Here’s the data on construction cost overruns, in percentage terms. The size of the bars represents the number of projects. Bars to the right of the black line indicate projects where costs were higher than expected. As you can see, costs were higher than expected for the vast majority of projects – sometimes to a quite significant degree (i.e. over 100% more expensive than planned).

Road cost overrun chart

And here’s a similar chart for benefit overruns/underruns. This shows that although estimates of benefits have in some cases been wrong by a quite large amount, most of the errors are clustered closer to the zero line. This shows that while NZTA or transport agencies often miss the mark on their estimates of benefits, the errors are sometimes positive and sometimes negative. In other words, optimism bias seems to be less pervasive when estimating benefits than when estimating costs.

Road benefit overruns chart

This data has (or should have) important implications for the way we plan and fund transport projects. It suggests that it’s necessary to be much more conservative when estimating the costs and benefits of road projects. This is especially important in light of the fact that NZTA’s funding is being devoted in large part to major motorway projects – the kind of “megaprojects” that Flybjerg identifies as posing the greatest risks for good project evaluation.

Unfortunately, NZTA stopped publishing post-implementation reviews in 2012, so it’s impossible to say whether agencies have used this data to refine their cost estimates. I hope they have, but there are indications that optimism bias is still running rampant. Take, for example, NZTA’s long-term forecasts of road traffic and public transport patronage, which blithely disregard the market realities. Or, more concretely, there’s the strange case of the Additional Waitemata Harbour Crossing traffic forecasts, which Matt picked up on a few years ago.

A 2010 business case for the AWHC, which would be New Zealand’s most expensive infrastructure project of all time, found that the project’s benefit-cost ratio was a mere 0.4 to 0.6. (Indicating that it costs about twice as much as it returns in benefits.) But, as it turns out, this figure was based on traffic modelling that overestimated actual traffic across the bridge in 2008 by almost 10% – in spite of the fact that the actual data was available at that point. That’s some serious optimism bias right there…

Ak Harbour Bridge Traffic volumes

Auckland Harbour Bridge Traffic volumes (actual and forecast)

Finally, it’s also worth noting that Flyvbjerg finds that cost overruns (and benefit underruns) tend to be a more serious issue for rail projects than for road projects, especially in the United States. Unfortunately, we simply haven’t completed enough rail projects to robustly evaluate whether the same holds true in New Zealand. However, there are some signs that recent public transport infrastructure projects have outperformed their business cases – as seen in NZTA’s post-implementation review of the Northern Busway and booming ridership at Britomart.

Environmental effects of an Additional Waitemata Harbour Crossing

The additional Waitemata Harbour crossing is a crazy project for a variety of reasons. The blog has noted before that the project is both completely unaffordable and totally unnecessary because of the lack of the actual benefits when you look at the detail. One thing that hasn’t been noted before however is the huge environmental impacts this project will have the coastline, both and the northern and southern end.

In 2010 an extensive study was carried out, which outlined the major options, looking at both bridge and tunnel options. This was the study that finally put an end to the even more ridiculous bridge idea. Usefully the study for the first time provided some detailed plans of what each option would look like on the ground. The issues is not so much the tunnel itself, but the complex arrangements required to allow for traffic merging between the different routes at the north end south ends. To recap the existing bridge will be used only for city bound traffic, and the new tunnel will be directed straight to the congestion at spaghetti junction.

AWHC north of Onewa

 

The plan above shows the motorway between Akoranga Drive (left), and Onewa Road (just out of picture to the right). The northernmost line is the railway line, however would be sure to take up much less space just built as a rail corridor, and would have a much higher capacity. The red hatched area is all of the land that would be reclaimed, while green is new viaducts or bridges. This would result in the corridor taking up twice as much space as it does now. As for what this would mean, this is the current view in the area. The large area of coastline to the right would be reclaimed.

P1050458

Looking north from public footbridge accessible from east end of Exmouth Road.

This next plan shows the area in the vicinity of the Onewa Road interchange, as well as the tunnel portals of both rail (left) and road (right). Again a huge amount of reclamation occurs.

AWHC Sulhur Beach

However what is hidden beneath the plans is the total destruction of Sulphur Beach and the marina located there.

P1050446

Looking towards the city from public path alongside motorway. Accessible from Sulphur Beach and Tennyson St beside police station.

Currently this beautiful area is not well known. However in a few years this will very likely change. With Skypath to go ahead within the next few years, this will be the route of Seapath, which would give a great easy link through to Takapuna. Once that happens people will appreciate this area much more, and won’t like to see it disappear under 6 lanes of motorway.

This area will also become a large construction yard, potentially for about 5 years. This will have major effects on areas of Northcote Point, with a large number of houses looking straight into the area. Their seaviews may well be replaced with views of more motorway lanes and flyovers. People on the Bayswater side of the harbour would also have their views affected negatively.

P1050431

View from Beach Road on Northcote Point towards area of sea to be reclaimed

On the south side of the harbour things aren’t much better. Around Westhaven marina there is yet more reclamation. The yet to open Westhaven Promenade will have to be completely rebuilt, with part of the marina needing to be reclaimed as even more width is required to account for the sweeping motorway curves. The extra width required is highlighted by the need to extend the Jacobs Ladder footbridge by about 50% so people can still cross the motorway corridor. A number of marine related businesses along Westhaven Drive will also disappear, as the road needs to be pushed north to give the corridor the space it requires.

AWHC Westhaven

The Landscape and Visual report prepared for NZTA summarises the issues that will arise:

The landscape of Shoal Bay and the northern sector will be significantly affected by the scale and magnitude of roading and reclamation. Effects are: changes to landforms and natural features including increased separation of the bay from; loss of beaches, reefs, and open spaces; impacts on cliffs (including diminution of scale and loss of vegetation); loss of natural vegetation and potential change due to weed infestation; diminished/decreased experience and appreciation of natural landscape for travellers. In addition structures such as flyovers, bridges, tunnel portals, buildings and vent stacks are all expected to have adverse effects on existing landscape character and alter the balance between the natural and manmade landscape. The cultural and heritage of the existing landscape will also be affected by changes in the southern sector, particularly in and around Victoria Park. Such changes will include loss of buildings and trees but could also include positive effects due to the removal of the existing flyover.

Unfortunately it makes no attempts to actually visualize what the effects would be, including the vent stack, which would be a very dominant feature. Note 35 metres is about 10 stories high!

” Vent building estimated to be 70m long by 30m wide by 20m high and stacks 35m high”

The stack was rather contentious during the Waterview proposal due to the fumes of a high volume of traffic all begin released in a concentrated area. They will be located at the tunnel portals. One will be in the vicinity of Sulphur Beach, near where the second photo above was taken from the walkway.

Vent Building north

The southern vent stack will be between Beaumont St and Westhave Drive, where the Crombie and Lockwood building is (opposite Air New Zealand).

Vent Building

While an additional rail crossing will require some small reclamation, it will be a large magnitude less than what is required for the road crossings. This is because 2 tracks take the same space as 2 motorway lanes, and there will be no need for complex ramps and mixing of lanes, and of course there will be no need for huge vent stacks.

Hopefully this post will highlight a number of the major effects this project will have on the environment and landscape. Surely this will make some North Shore, St Mary’s Bay and inner city residents think twice about the need for this project, considering the effect on their backyard and harbour. This should also awaken reporters, including one John Roughan who was horrified at the sight of a comparatively tiny reclamation for the busway in 2007.

“Hideously inefficient” road spending in Australia

For an interesting Friday afternoon read, here‘s an article from Australia which may ring true for New Zealand as well – especially given the possibility that National is considering an absolutely daft idea, creating a second road-only Waitemata Harbour crossing. From The Age:

More than $20 billion a year of national road funding is being spent in a “hideously inefficient” manner, according to a leaked assessment by Australia’s independent infrastructure umpire.

The Infrastructure Australia report, obtained by Fairfax Media, has also delivered a scathing critique of “monopoly” state-run road entities such as VicRoads, claiming a culture of resisting reform has led to a situation  in which political leaders are held “captive” to demands for more funding.

I don’t know about New Zealand’s current political leaders being held captive… unless perhaps it’s a case of Stockholm Syndrome?
The report was titled “Spend more, waste more, Australia’s roads in 2014: moving beyond gambling”, which seems like a fairly provocative title for a report. It seems fairly likely that someone will get a clip round the ear and a more mundane title (and report) released later this year. Reading on:

“The unhealthy focus of road agencies appears set on ‘getting, controlling and spending’ more taxpayer money, rather than questioning efficiency or value to the motorist and governments,” the report says.

The report, which claimed Australia has a “gambler’s addiction to roads”, said national road spending is now outstripping revenue raised through road-related taxes and charges, warning “Australia’s thirst for roads” would come at the expense of other services as the gap continues to widen. In the four years to June 30, 2012, road spending outstripped road revenue by $4.5 billion.

Of course, we’re in a similar position in New Zealand, with National now reaching beyond the NLTF to pay for its spending on roads.

It suggested there was little consideration of whether Australia’s demands for new roads should be satisfied, and argued that rail funding had missed out as a result.

“The current Australian system assumes that roads are an answer to most transport problems and seeks more and more funding to that end, with little consideration of alternatives that most other developed parts of the world enjoy, such as significant heavy intercontinental rail networks and dominant heavy mass transit systems.”

“[Road proposals seen by Infrastructure Australia] were almost universally poor, in that they lacked any cost-benefit rigour whatsoever,” it said. “The real problem is that road agencies and other road project proponents in industry and the community spend next to no effort examining what problems their projects and plans are trying to solve, other than the perceived problem that they do not have enough road funding.”

Overall, a fairly damning indictment of Australian transportation policy, and we’ll be eagerly waiting for the final (or at least, public) version of the report.

Accelerating the Additional Harbour Crossing project?

Yesterday was a busy day for transport news. Alongside Gerry Brownlee’s strange airport escapade, Labour Transport Spokesman Phil Twyford dropped a bit of a bombshell in relation to the possible acceleration of the Additional Waitemata Habour Crossing (AWHC) project as well as the exclusion of the project’s rail component:

Labour Transport spokesperson Phil Twyford says it has been leaked to him that John Key will rule out a rail option when announcing an accelerated timeframe for Auckland’s $5 billion second harbour crossing next month.

“I understand the Government’s plan is for a roads-only option which would be a giant wasted opportunity to connect rail to the North Shore and link it up with the City Rail Link and the rest of the regional rail network,” says Mr Twyford.

“Aucklanders want their cars but they also realise it is past time to start investing in a modern public transport network. We’ve seen that in recent polls.

“This Government has not initiated a single new public transport infrastructure project in Auckland since it came to office.

“They announced an $800 million transport package for Auckland in the Budget but there wasn’t one public transport project in it. They even rejected officials’ advice to extend the wildly successful Northern Busway.

“If National goes ahead with the second harbour crossing but doesn’t include rail, it would be a major blunder on a par with National’s decision to build the first harbour bridge on the cheap, with clip-ons needed shortly after,” says Phil Twyford.

There’s been no confirmation of the announcement by the government. The Campaign for Better Transport’s media release in response highlights a number of the concerns we’ve had about this project over the past months and years:

The Campaign for Better Transport said today that the Government’s idea of an additional road only Waitemata Harbour Crossing hasn’t been thought through.

“We all know that the Northern Motorway and approaches are notoriously congested at peak times, so local support probably stems from the belief that this congestion will somehow be solved,” said spokesperson Cameron Pitches.

“However, the net effect of a road only crossing will be that in the morning peak, the Auckland CBD will be flooded with thousands of extra single occupant cars looking for a car park. The Central Motorway Junction will also be a bottleneck without more lanes, but there is no room for more.

“And in the evening peak the already congested Northern Motorway will grind to a halt, as six lanes converge into three.”

Mr Pitches says a far better solution would be a rail only crossing that would extend from the City Rail Link to Albany on the North Shore.

“The Northern Busway is enormously popular and is a great example of a system that can carry far more people at peak times than single occupant cars. High capacity rail would be the logical next step.”

Mr Pitches said that a recent report identified that the cost of a rail link connecting the City Rail Link to Albany on the North Shore would be about $2.5bn.

“It is clear that the Government’s proposal and any alternatives have not been through Treasury’s better business case process.  There is no urgency with the project either as the yet to be completed Western Ring Route is designed to reduce traffic volumes on the bridge,” said Mr Pitches.

The Goverment is yet to make an official announcement on how a new crossing would be funded, but Mr Pitches suspects it would have to be tolled due to the multi-billion dollar cost of the project.

“The Government also needs to be honest and reveal how much the toll will be for the new crossing, and if the current Harbour Bridge will be tolled as well.”

“It just makes no sense.  The Government has just been caught out not doing a comprehensive assessment of alternatives for the Basin Reserve.  You would think they would want to avoid making the same mistake twice,” concludes Mr Pitches.

Our most comprehensive criticism of the project is in a recent post here, with a quick summary being that it seems Auckland’s most expensive ever proposed project is likely to make things worse for traffic rather than better, particularly by feeding thousands more cars into a city centre that can’t cope with any more of them.

If it does get announced as speculated would Len Brown be brave enough to say no to it ? Given his previous comments I don’t think so. Let’s hope the announcement – if there even is one – only relates to progressing route protection for the project, which was already announced last year by the Prime Minister.

How the AWHC is a waste of $5.3 billion

Update 24/7/14 – Given the rumours flying around today about Government announcing the possible acceleration of this project, we have made this earlier post “sticky” while we write up a new post on the issue for tomorrow.

This is the first of a couple of posts looking more closely at the Additional Waitemata Harbour Crossing project and how we could do it differently.

Last week there was some renewed debate over the merits of the Additional Waitemata Harbour Crossing (AWHC) project, due to former Local Government Minister Michael Bassett suggesting it should start nearly immediately and made a lot more sense than the City Rail Link. I outlined why that particular argument is complete rubbish previously, but I think it’s worth delving back into exactly why AWHC is an unnecessary, wasteful, counter-productive and completely stupid project. For the purposes of this post, I’m talking about the AWHC project’s roading components as proposed in quite a lot of detail here by NZTA.

Continue reading How the AWHC is a waste of $5.3 billion